A required inspection fails and the inspector lists corrections. What should occur before the work is treated as approved?

Correct Answer

C) Correct the cited items and obtain the required reinspection or approval

Failed inspections require correction and approval through the inspection process.

Answer Options
A
Close the walls and submit the correction list with the final payment package after the work is hidden
B
Ask the original bidder to withdraw its bid
C
Correct the cited items and obtain the required reinspection or approval
D
Use the subcontractor's daily report as the approval record

Why This Is the Correct Answer

Failed inspections require correction and approval through the inspection process.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.