The building official identifies work that appears unsafe or unauthorized under the permit. Which code-administration authority is most relevant?

Correct Answer

D) The building official's stop-work or enforcement authority under the code

FBC administration gives the building official enforcement authority for unsafe or unauthorized work.

Answer Options
A
Use the bid opening rule for withdrawal before receipt of bids as the response to unsafe field work
B
The subcontractor payment timing clause in AIA A401
C
The schedule of values used only for progress billing
D
The building official's stop-work or enforcement authority under the code

Why This Is the Correct Answer

FBC administration gives the building official enforcement authority for unsafe or unauthorized work.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.