A bid form lists an alternate, but the GC does not intend to take exception to it. What is the safest bid-administration practice?

Correct Answer

C) Complete the alternate line exactly as the instructions require

Bid forms should be completed according to the bidding instructions to avoid ambiguity or nonresponsiveness.

Answer Options
A
Leave the alternate line blank and explain it after bid opening
B
Remove the alternate from the bid form before submission
C
Complete the alternate line exactly as the instructions require
D
Submit only the base bid and ask the owner to infer the alternate price

Why This Is the Correct Answer

Bid forms should be completed according to the bidding instructions to avoid ambiguity or nonresponsiveness.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.