A partition estimate requires 3,250 lf of metal studs before waste. With 8% waste, what quantity should be carried?

Correct Answer

D) 3,510 lf

Apply the waste percentage to the measured linear footage.

Answer Options
A
3,250 lf
B
3,445 lf
C
3,575 lf
D
3,510 lf

Why This Is the Correct Answer

Apply the waste percentage to the measured linear footage.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.