A crew installs 720 sf of acoustic ceiling per day. The project includes 5,040 sf. How many crew days should be planned?

Correct Answer

B) 7 crew days

Divide total quantity by daily productivity.

Answer Options
A
6 crew days
B
7 crew days
C
8 crew days
D
9 crew days

Why This Is the Correct Answer

Divide total quantity by daily productivity.

Why the Other Options Are Wrong

Option A: 6 crew days

6 crew days is below the supported result for crew duration; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 8 crew days

8 crew days is above the supported result for crew duration; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 9 crew days

9 crew days is above the supported result for crew duration; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Measure to divide, adjust for daily, then let Interiors Estimate set the finish line.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Estimating labor productivity; crew duration; match the project role and timing before choosing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.