A plumbing proposal is low but excludes sleeves, firestopping, and test reports that other proposals include. What is the proper estimating step?

Correct Answer

D) Clarify exclusions and normalize scope before using the proposal in the bid recap

Scope review identifies exclusions and qualifications before a proposal is used for bid pricing.

Answer Options
A
Accept the low price because exclusions always transfer to the owner
B
Delete the excluded items from the project without notifying the design team or listing the scope gap in the bid recap
C
Carry the proposal unchanged and rely on final payment to fix the gap
D
Clarify exclusions and normalize scope before using the proposal in the bid recap

Why This Is the Correct Answer

Scope review identifies exclusions and qualifications before a proposal is used for bid pricing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.