Contract AdminPreconstructionmedium27% of exam part

Base labor wages for a bid package are $48,500. Labor burden is estimated at 28%. What total burdened labor cost should be used?

Correct Answer

C) $62,080

Add the burden percentage to base wages.

Answer Options
A
$57,420
B
$60,150
C
$62,080
D
$64,840

Why This Is the Correct Answer

Add the burden percentage to base wages.

Why the Other Options Are Wrong

Option A: $57,420

$57,420 is below the supported result for labor burden; it likely omits allowance, conversion, coverage, or final round-up.

Option B: $60,150

$60,150 is below the supported result for labor burden; it likely omits allowance, conversion, coverage, or final round-up.

Option D: $64,840

$64,840 is above the supported result for labor burden; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Measure to add, adjust for percentage, then let Estimator Checks set the finish line.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Estimating labor cost; labor burden; match the project role and timing before choosing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.