EstatePass
Contract AdminPreconstructionmedium27% of exam part

A loading apron is 210 ft by 38 ft. The paving subcontractor prices by square yard, and the estimator carries 5% waste. What quantity should be carried?

Correct Answer

C) 931 sy

Convert square feet to square yards, then add waste.

Answer Options
A
887 sy
B
912 sy
C
931 sy
D
980 sy

Why This Is the Correct Answer

Convert square feet to square yards, then add waste.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.