A sheathing crew can install 450 sf per day. The bid quantity is 3,600 sf and the crew cost is $2,240 per day. What labor cost should be carried?
Correct Answer
C) $17,920
Divide the quantity by daily production, then multiply by the crew-day cost.
Why This Is the Correct Answer
Divide the quantity by daily production, then multiply by the crew-day cost.
Why the Other Options Are Wrong
Option A: $16,800
$16,800 is below the supported result for labor productivity; it likely omits allowance, conversion, coverage, or final round-up.
Option B: $18,670
$18,670 is above the supported result for labor productivity; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Option D: $20,160
$20,160 is above the supported result for labor productivity; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Labor Productivity cart for Estimator Prices: divide first, daily second, whole units last.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Estimating labor productivity and crew cost; match the project role and timing before choosing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?