Field indirect costs include $58,900 supervision, $21,600 temporary utilities, and $14,750 field office costs. What general conditions total is budgeted?

Correct Answer

D) $95,250

The listed general conditions items add to $95,250.

Answer Options
A
$82,500
B
$88,250
C
$90,500
D
$95,250

Why This Is the Correct Answer

The listed general conditions items add to $95,250.

Why the Other Options Are Wrong

Option A: $82,500

$82,500 is below the supported result for general conditions subtotal; it likely uses the wrong base, period, or account bucket.

Option B: $88,250

$88,250 is below the supported result for general conditions subtotal; it likely uses the wrong base, period, or account bucket.

Option C: $90,500

$90,500 is below the supported result for general conditions subtotal; it likely uses the wrong base, period, or account bucket.

Memory Technique

Estimator Summarizes money test: bucket before math for general.

Reference Hint

Open-book path: tab Builder's Guide to Accounting, 2001 to Section Two, Accounting for Costs and Expenses, Accounting for Overhead; use the job ledger figures in the stem and recompute the same accounting measure.

Was this explanation helpful?

More Business & Finance Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.