An Arizona contractor has 3 employees with a total annual payroll of $180,000. The workers compensation rate for their classification is $4.50 per $100 of payroll. What is the annual workers compensation premium?
Correct Answer
A) $8,100
Premium = ($180,000 ÷ $100) × $4.50 = 1,800 × $4.50 = $8,100
Why This Is the Correct Answer
Premium = ($180,000 ÷ $100) × $4.50 = 1,800 × $4.50 = $8,100
More az-supplement Questions
What is the current minimum bond amount required for a residential contractor license in Arizona?
A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?
Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?
Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?
A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?
A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?
According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?
A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?
A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?
A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Under A.R.S. 33-981, a contractor must file a preliminary 20-day notice for lien rights. If materials are first delivered on March 15th and labor begins March 20th, what is the deadline to serve the preliminary notice?
Next Question
A subcontractor performs electrical work valued at $8,500 on a residential project. The general contractor fails to pay. Under Arizona lien law, what is the maximum amount the subcontractor can claim in their mechanic's lien?