EstatePass
ArizonaAZ B&Lmedium100% of exam part

Under A.R.S. 33-981, a contractor must file a preliminary 20-day notice for lien rights. If materials are first delivered on March 15th and labor begins March 20th, what is the deadline to serve the preliminary notice?

Correct Answer

C) April 4th

The preliminary notice must be served within 20 days of first furnishing labor or materials. Since materials were delivered first on March 15th, the deadline is April 4th (20 days later).

Answer Options
A
March 25th
B
April 15th
C
April 4th
D
April 9th

Why This Is the Correct Answer

The 20-day clock starts from the date labor or materials are FIRST furnished, whichever occurs earlier. Materials were delivered March 15th — five days before labor began — so the triggering date is March 15th. Adding 20 calendar days: March 15 + 20 = April 4th. That is the statutory deadline.

Why the Other Options Are Wrong

Option A: March 25th

March 25th is only 10 days after March 15th. This would represent half the allowed period and does not reflect the 20-day statutory requirement under A.R.S. 33-981.

Option B: April 15th

April 15th is 31 days after March 15th, exceeding the 20-day window. It may appear attractive if someone mistakenly counts from the labor start date (March 20 + 26 days), but neither calculation produces a valid legal deadline.

Option D: April 9th

April 9th is 25 days after March 15th, or 20 days after the labor start of March 20th. This is a classic trap: candidates who count from the labor start rather than the material delivery date will arrive at this incorrect answer.

Memory Technique

Think 'FIRST furnishing fires the clock.' Materials hit the site first on March 15 — that day pulls the trigger. Count exactly 20 days forward: March 15 → April 4.

Was this explanation helpful?

More Arizona Questions

What is the current minimum bond amount required for a residential contractor license in Arizona?

A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?

Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?

Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?

A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?

A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?

According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?

A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?

A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?

A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.