A subcontractor performs electrical work valued at $8,500 on a residential project. The general contractor fails to pay. Under Arizona lien law, what is the maximum amount the subcontractor can claim in their mechanic's lien?
Correct Answer
D) $8,500 plus interest and attorney fees
Under A.R.S. 33-981, a mechanic's lien can include the amount due plus reasonable interest and attorney fees incurred in collection.
Why This Is the Correct Answer
Under A.R.S. 33-981, a mechanic's lien may include the contract amount owed plus reasonable interest accrued and attorney fees incurred in pursuing collection. This means the subcontractor is not limited to the flat $8,500 but is entitled to the full cost of enforcing their right to payment, making option D the most complete and legally accurate answer.
Why the Other Options Are Wrong
Option A: $8,500 plus statutory penalties
While the lien includes fees, 'statutory penalties' is not the correct terminology under Arizona lien law. A.R.S. 33-981 specifies interest and attorney fees β not penalties. This option uses imprecise language that does not match the statute.
Option B: The full contract amount between owner and general contractor
A subcontractor's lien is limited to the amount owed to that subcontractor, not the full contract amount between the owner and the general contractor. Claiming the full owner-GC contract value would allow a sub to lien for work they did not perform, which is not permitted.
Option C: $8,500 only
$8,500 only is too narrow. While the base amount is correct, Arizona law explicitly allows the lienholder to recover interest and attorney fees in addition to the contract amount. Limiting the lien to the flat contract price ignores the statutory provisions for collection costs.
Memory Technique
Mechanic's lien = What you're OWED + Interest + Attorney Fees. Remember 'IAF' β Interest And Fees are always included under Arizona lien law. The lien covers the full cost of getting paid, not just the original invoice.
More Arizona Questions
What is the current minimum bond amount required for a residential contractor license in Arizona?
A contractor files a preliminary 20-day notice on January 15th for work that began on January 10th. The preliminary notice was delivered to the owner on January 18th. Under A.R.S. 33-981, is this notice valid for lien purposes?
Under Arizona law, which entity has the authority to investigate complaints against licensed contractors and impose disciplinary actions?
Under Arizona ROC regulations, what is the maximum amount a residential contractor can collect as a down payment before beginning work?
A contractor's license expires on June 30th. The contractor submits a renewal application on July 15th. Under Arizona ROC regulations, what penalty applies?
A contractor's workers compensation policy lapses for 15 days due to non-payment of premiums. Three employees are injured during this period, resulting in $85,000 in medical costs. Under Arizona law, what is the contractor's potential liability?
According to A.R.S. Title 32, which of the following can serve as a qualifying party for multiple contracting businesses?
A residential contractor enters into a contract for $15,000 to remodel a kitchen. Under Arizona law, what is the required down payment limitation?
A residential contractor completed $45,000 in work and materials. The homeowner paid $35,000 but disputes the remaining $10,000. How long does the contractor have to file a mechanics lien after recording the notice of completion?
A contractor has 8 employees working on various projects. The annual workers' compensation premium is $24,000. If the contractor fails to maintain coverage, what is the maximum daily penalty exposure?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An Arizona contractor has 3 employees with a total annual payroll of $180,000. The workers compensation rate for their classification is $4.50 per $100 of payroll. What is the annual workers compensation premium?
Next Question
A residential contractor's qualifying party leaves the company. Under Arizona law, how long does the contractor have to replace the qualifying party before their license becomes inactive?