A preliminary notice for a mechanics lien must be served within how many days after first furnishing labor or materials to a project?
Correct Answer
B) 20 days
California Civil Code requires preliminary notices to be served within 20 days after first furnishing labor, services, equipment, or materials to the work of improvement.
Why This Is the Correct Answer
California Civil Code requires that a preliminary notice (also called a 20-day preliminary notice) be served within 20 days after a claimant first furnishes labor, services, equipment, or materials. Serving this notice is a prerequisite to later recording a mechanics lien — missing the 20-day window can extinguish lien rights for work performed before the notice.
Why the Other Options Are Wrong
Option A: 30 days
30 days is incorrect. The preliminary notice must be served within 20 days, not 30. Confusing this with other 30-day periods (e.g., stop payment notice timing) is a common error.
Option C: 15 days
15 days is too short. While some states use shorter windows, California's preliminary notice window is specifically 20 days.
Option D: 10 days
10 days is too short. No California lien-related preliminary notice requires only 10 days.
Memory Technique
20-day preliminary notice = 'first 20 days on the job.' Think of it as announcing your presence on the project within the first 20 days. After the job ends, you have 90 days to record the actual lien. Two different deadlines, two different purposes.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor completes $8,500 worth of kitchen remodeling work on March 15th. The homeowner disputes $2,000 of the charges. Under California prompt payment law, when must the undisputed portion be paid?
Next Question
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
