CaliforniaContractsmedium20% of exam part

A contractor completes $8,500 worth of kitchen remodeling work on March 15th. The homeowner disputes $2,000 of the charges. Under California prompt payment law, when must the undisputed portion be paid?

Correct Answer

A) Within 30 days of completion

Under California prompt payment requirements, the undisputed portion ($6,500) must be paid within 30 days of completion, even when there are disputes over other portions.

Answer Options
A
Within 30 days of completion
B
Within 7 days of completion
C
Within 21 days of completion
D
Within 10 days of completion

Why This Is the Correct Answer

Option A is correct. California prompt payment law requires that the undisputed portion of a contractor's payment be made within 30 days of completion, even when a portion of the invoice is in dispute. The homeowner cannot withhold the undisputed $6,500 simply because $2,000 is contested — the two amounts are treated separately.

Why the Other Options Are Wrong

Option B: Within 7 days of completion

Option B (7 days) is far too short and does not reflect California's prompt payment statute for private residential work. Seven-day deadlines apply in certain subcontractor payment contexts or other specific scenarios, not to the owner-to-contractor payment on a completed job.

Option C: Within 21 days of completion

Option C (21 days) is not the correct deadline under California prompt payment law for this scenario. While 21 days appears in some payment contexts (such as certain public works or retention release timelines), the correct deadline for payment of the undisputed amount on private work upon completion is 30 days.

Option D: Within 10 days of completion

Option D (10 days) has no basis in California prompt payment law for owner-to-contractor payment on a completed private project. This may be confused with short payment windows in other contexts or states.

Memory Technique

Remember '30 days = done and paid.' Once the job is complete, the clock starts. Even if there's a fight over part of the bill, the owner has 30 days to pay what isn't disputed. Think of it like a restaurant bill — you still pay for the dishes you enjoyed, even if you're arguing about the one that was wrong.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.