A North Carolina contractor files a claim of lien on real property. Within how many days must the contractor serve a copy of the claim of lien on the owner of the real property?

Correct Answer

D) 30 days

Under NC lien law, a copy of the claim of lien must be served on the owner within 30 days of filing.

Answer Options
A
60 days
B
120 days
C
90 days
D
30 days

Why This Is the Correct Answer

Under North Carolina lien law, after filing a claim of lien with the clerk of court, the contractor must serve a copy of that claim on the property owner within 30 days of filing. Failure to timely serve the owner can jeopardize the validity of the lien.

Why the Other Options Are Wrong

Option A: 60 days

60 days is twice the required period. While 60 days appears in other contexts in lien law (such as the deadline to file the lien itself), it is not the service deadline after filing.

Option B: 120 days

120 days is the timeframe to commence a lien enforcement action (lawsuit) after filing, not the deadline to serve the property owner with a copy of the claim. Confusing enforcement deadlines with service deadlines is a common error.

Option C: 90 days

90 days does not correspond to the service requirement in NC lien law. This number may be confused with grace periods in other parts of contractor licensing or lien statutes.

Memory Technique

File it, then serve it fast β€” 30 days to notify the owner. 'Filing feeds the lien, serving seals the deal in 30.' Think of 30 as the 'notification number' in NC liens.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.