Under NC building codes, what is the minimum required inspection frequency for concrete placement on a commercial project?

Correct Answer

A) Before, during, and after each concrete pour

NC building codes require inspections before, during, and after each concrete pour to ensure compliance with structural requirements.

Answer Options
A
Before, during, and after each concrete pour
B
Weekly regardless of concrete activity
C
Daily during concrete operations
D
Only after completion of concrete work

Why This Is the Correct Answer

North Carolina building codes require inspections at three stages of each concrete pour: before placement begins (to verify formwork, reinforcement, and substrate), during placement (to monitor consolidation and placement methods), and after placement (to verify finish and compliance). This three-stage requirement applies to each individual pour, not on a calendar basis.

Why the Other Options Are Wrong

Option B: Weekly regardless of concrete activity

Weekly inspections regardless of activity would leave many concrete pours uninspected if multiple pours occur in a week, or result in wasteful inspections when no concrete work is occurring. NC code ties inspections to the concrete activity itself, not to a fixed calendar.

Option C: Daily during concrete operations

Daily inspections during concrete operations would miss the critical pre-pour verification stage and would be insufficient when multiple pours occur in a single day. The code requires coverage for each individual pour event.

Option D: Only after completion of concrete work

Post-completion inspection only is the least protective approach and would allow defects in formwork, rebar placement, or pour technique to go undetected until the concrete has already hardened β€” at which point corrections are extremely costly or impossible.

Memory Technique

For NC concrete inspections, think BDA: Before, During, After β€” applied to EACH pour. Three stages, every time, not once a day or once a week.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.