A contractor has 8 employees earning a combined $320,000 annually. The workers' compensation rate is $2.80 per $100. What is the monthly premium?
Correct Answer
D) $747
Annual premium = ($320,000 ÷ $100) × $2.80 = $8,960. Monthly premium = $8,960 ÷ 12 = $746.67, rounded to $747.
Why This Is the Correct Answer
The correct answer is D ($747). Step 1: Calculate annual premium = ($320,000 ÷ 100) × $2.80 = 3,200 × $2.80 = $8,960. Step 2: Calculate monthly premium = $8,960 ÷ 12 = $746.67, which rounds to $747.
Why the Other Options Are Wrong
Option A: $896
$896 is incorrect. This figure equals the annual premium divided by 10 ($8,960 ÷ 10), not divided by 12. A common error is dividing by 10 instead of 12 months.
Option B: $672
$672 is incorrect. This may result from dividing the payroll by 100 to get $3,200, then incorrectly treating this as the monthly payroll and multiplying by $2.80 ($3,200 × $2.10 = $6,720, divided by 10 = $672). The error chain involves using a wrong rate or divisor.
Option C: $560
$560 is incorrect. This could result from dividing $320,000 by 12 to get a monthly payroll ($26,667), then dividing by 100 ($266.67) and multiplying by $2.10 instead of $2.80, or from some similar computational shortcut that skips proper formula application.
Memory Technique
Two-step process: 'Annual first, then monthly.' Step 1: (Payroll ÷ 100) × rate = annual. Step 2: Annual ÷ 12 = monthly. For this problem: $320K ÷ 100 = $3,200; × $2.80 = $8,960/year; ÷ 12 = $746.67 ≈ $747/month.
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000: