A material supplier delivered $25,000 worth of lumber to a job site on January 10th. The project was completed on February 15th, and no notice of completion was recorded. What is the supplier's deadline to file a mechanics lien?
Correct Answer
D) May 17th
When no notice of completion is recorded, suppliers have 90 days from project completion to file a lien. February 15th + 90 days = May 17th.
Why This Is the Correct Answer
Under California Civil Code, when no notice of completion is recorded, material suppliers have 90 days from the date of project completion to file a mechanics lien. February 15 + 90 days = May 17th (February has 28 days in a non-leap year: 13 remaining days in Feb + 31 in March + 30 in April + 16 in May = 90 days, landing on May 17th).
Why the Other Options Are Wrong
Option A: April 15th
April 15th would be 59 days from February 15th, not 90 days. This is well short of the 90-day deadline and would cause a supplier to file prematurely or, if they waited thinking they had until April 15th, miss the actual calculation entirely.
Option B: June 14th
June 14th is 119 days from February 15th, which exceeds the 90-day window. Filing on June 14th would mean the lien rights have already expired by nearly a month, rendering the lien invalid.
Option C: May 15th
May 15th is 89 days from February 15thβone day short of the correct 90-day count. This is a close distractor designed to catch candidates who miscalculate the date math by failing to count correctly across month boundaries.
Memory Technique
No Notice of Completion = 90 days for everyone. Notice of Completion IS recorded = 30 days for subcontractors/suppliers, 60 days for direct contractors. No NOC = most time (90 days). Always count calendar days precisely.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Which of the following information is NOT required to be included in a home improvement contract under B&P Code 7159?
Next Question
A contractor completes a $18,000 deck project on March 15th. No notice of completion is filed. What is the last date the contractor can record a mechanics lien?