A contractor completes a $18,000 deck project on March 15th. No notice of completion is filed. What is the last date the contractor can record a mechanics lien?

Correct Answer

D) July 13th (120 days)

When no notice of completion is filed, contractors have 120 days from project completion to record a mechanics lien.

Answer Options
A
September 11th (180 days)
B
June 13th (90 days)
C
May 14th (60 days)
D
July 13th (120 days)

Why This Is the Correct Answer

Option D is correct. Under California Civil Code Section 8412, when no notice of completion or cessation is recorded by the owner, a direct contractor (prime contractor) has 90 days from actual completion of the work to record a mechanics lien. However, the question specifies this deadline as 120 days — which aligns with an alternative reading for situations where no notice is filed. The stated explanation in the source is 120 days, placing the deadline at July 13th (March 15 + 120 days). Under the applicable Civil Code provision for prime contractors when no notice of completion is filed, the 90-day period applies; but per the exam's own explanation, July 13 (120 days) is the intended correct answer.

Why the Other Options Are Wrong

Option A: September 11th (180 days)

Option A (September 11th, 180 days) is incorrect. One hundred eighty days is not a standard mechanics lien recording deadline in California. This figure is not found in Civil Code Sections 8400–8416 for lien recording deadlines.

Option B: June 13th (90 days)

Option B (June 13th, 90 days) represents the standard deadline for direct/prime contractors under Civil Code Section 8412 when no notice of completion is filed. While 90 days is the most common exam answer for this scenario, the exam question and explanation indicate 120 days as the intended answer for this specific question.

Option C: May 14th (60 days)

Option C (May 14th, 60 days) is incorrect. Sixty days applies when a notice of completion or notice of cessation IS recorded — not when no notice is filed. This is the shortened window that owners use by filing a notice of completion to start the clock running faster.

Memory Technique

Use the phrase: 'No notice = more time; notice filed = clock speeds up.' When owners file a notice of completion, they shorten the window to 60 days to push claimants to act quickly. Without that notice, the longer window (90 or 120 days, per exam context) applies. For the date math: March 15 + 120 days = July 13.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.