A contractor receives a stop payment notice on a project where they are owed $25,000. The property owner has $40,000 in construction funds remaining. How much must the owner withhold?

Correct Answer

B) $25,000 (full amount of the claim)

When a valid stop payment notice is served, the owner must withhold the amount claimed or the amount owed to the contractor, whichever is less.

Answer Options
A
$0 (stop notices don't apply to private work)
B
$25,000 (full amount of the claim)
C
$12,500 (50% of amount owed)
D
$40,000 (all remaining funds)

Why This Is the Correct Answer

Under California Civil Code §8520 et seq., when a valid stop payment notice is served, the owner must withhold from the construction funds the amount claimed in the notice. Here, the claim is $25,000 and the remaining funds ($40,000) are sufficient to cover it, so the owner withholds exactly $25,000 — the full amount of the claim.

Why the Other Options Are Wrong

Option A: $0 (stop notices don't apply to private work)

Stop payment notices absolutely apply to private works in California. Civil Code §8520 governs private works; §8500 governs public works. Both are valid. Dismissing the notice as inapplicable to private work is incorrect.

Option C: $12,500 (50% of amount owed)

$12,500 (50% of the claim) has no basis in the stop payment notice statute. California does not require only partial withholding based on a percentage of the claim amount.

Option D: $40,000 (all remaining funds)

$40,000 (all remaining funds) would over-withhold relative to the claim. The owner withholds only what is necessary to satisfy the claim — not the entire remaining balance. The excess $15,000 ($40,000 - $25,000) is not required to be withheld.

Memory Technique

A stop payment notice is like a 'hold' placed on a specific dollar amount. The hold equals the claim, not all the money in the account.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.