A contractor completes $8,500 worth of electrical work on a commercial building. The property owner fails to pay after 30 days. What is the deadline for the contractor to record a mechanics lien under California Civil Code?
Correct Answer
B) 90 days after completion
Under Civil Code Section 8416, a contractor must record a mechanics lien within 90 days after completion of the work of improvement.
Why This Is the Correct Answer
Under California Civil Code Section 8416, a direct contractor (prime contractor) must record a mechanics lien within 90 days after completion of the work of improvement. Missing this deadline extinguishes the lien right entirely, regardless of the amount owed.
Why the Other Options Are Wrong
Option A: 30 days after completion
30 days after completion is not the mechanics lien deadline for direct contractors. While some preliminary notice deadlines are shorter, the lien recording window for contractors who have directly contracted with the owner is 90 days from completion.
Option C: 60 days after completion
60 days is the mechanics lien deadline that applies to subcontractors and material suppliers (claimants who do not have a direct contract with the owner). A direct contractor, as in this scenario, has the longer 90-day window.
Option D: 120 days after completion
120 days exceeds the statutory deadline. No provision allows a 120-day lien recording period under California Civil Code for standard construction completion scenarios. Waiting 120 days would result in the lien right being lost.
Memory Technique
Remember: 'Direct = 90, Indirect = 60.' A direct contractor has a direct line to the owner and gets 90 days. A sub or supplier is one step removed and gets only 60 days. Think: the closer you are to the owner, the more time you get to file.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor receives a stop payment notice on a project where they are owed $25,000. The property owner has $40,000 in construction funds remaining. How much must the owner withhold?
Next Question
Under California Civil Code Section 8000-9566, what is the maximum time limit for enforcing a recorded mechanics lien through legal action?