EstatePass
LouisianaLA Supplementhard100% of exam part

A contractor is building a house in a flood zone in Louisiana. The base flood elevation is 8 feet, and the lowest floor must be elevated 2 feet above base flood elevation. If the existing grade is 4 feet above sea level, what is the minimum elevation required for the lowest floor?

Correct Answer

D) 10 feet

The lowest floor must be at base flood elevation (8 feet) plus 2 feet of freeboard = 10 feet above sea level minimum elevation.

Answer Options
A
14 feet
B
12 feet
C
8 feet
D
10 feet

Why This Is the Correct Answer

The required lowest floor elevation is determined by the base flood elevation (BFE) plus any required freeboard, measured above sea level (the vertical datum). BFE = 8 feet above sea level. Required freeboard = 2 feet. Therefore minimum floor elevation = 8 + 2 = 10 feet above sea level. The existing grade of 4 feet is irrelevant to the calculation — it describes the existing ground level, not the required floor elevation. The floor must reach 10 feet regardless of grade.

Why the Other Options Are Wrong

Option A: 14 feet

14 feet results from incorrectly adding the grade (4 feet) + BFE (8 feet) + freeboard (2 feet). The grade does not factor into the minimum floor elevation formula; only BFE + freeboard determines the required elevation above sea level.

Option B: 12 feet

12 feet results from adding grade (4 feet) + BFE (8 feet), ignoring the freeboard requirement. This error omits the mandatory 2-foot freeboard above BFE that Louisiana requires.

Option C: 8 feet

8 feet is the BFE itself — the base flood elevation with no freeboard added. This would be the minimum under FEMA's basic NFIP requirement, but the question specifies that the lowest floor must be 2 feet ABOVE BFE, making the correct answer 10 feet, not 8.

Memory Technique

Flood elevation formula: BFE + Freeboard = Minimum Floor Elevation (above sea level). Ignore the grade in the calculation — the grade is the 'before,' the BFE + freeboard is the 'after.' 8 + 2 = 10 feet.

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.