A contractor is building a house in a flood zone in Louisiana. The base flood elevation is 8 feet, and the lowest floor must be elevated 2 feet above base flood elevation. If the existing grade is 4 feet above sea level, what is the minimum elevation required for the lowest floor?
Correct Answer
D) 10 feet
The lowest floor must be at base flood elevation (8 feet) plus 2 feet of freeboard = 10 feet above sea level minimum elevation.
Why This Is the Correct Answer
The lowest floor must be at base flood elevation (8 feet) plus 2 feet of freeboard = 10 feet above sea level minimum elevation.
More la-supplement Questions
A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?
A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?
A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?
Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?
A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?
Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?
Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?
A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?
A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?
A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A material supplier delivered $15,000 worth of lumber on January 10th to a private construction project. The project was completed on March 1st. Under Louisiana's Private Works Act, what is the latest date the supplier can file their statement of claim?
Next Question
A subcontractor completes electrical work on a Louisiana private project on March 15th. The general contractor's work is completed on April 30th. By what date must the subcontractor file their lien claim?
