EstatePass
LouisianaLA Supplementmedium100% of exam part

A subcontractor completes electrical work on a Louisiana private project on March 15th. The general contractor's work is completed on April 30th. By what date must the subcontractor file their lien claim?

Correct Answer

D) June 29th

Subcontractors must file lien claims within 60 days of completion of the general contractor's work, not their own work. April 30th + 60 days = June 29th.

Answer Options
A
May 30th
B
July 30th
C
May 14th
D
June 29th

Why This Is the Correct Answer

Under Louisiana's Private Works Act, subcontractors must file their lien claim within 60 days of the completion of the general contractor's work—not within 60 days of their own last day of work. The GC completed work on April 30th; adding 60 days yields June 29th as the filing deadline.

Why the Other Options Are Wrong

Option A: May 30th

May 30th represents 30 days after April 30th (the GC's completion date), which is only half the allowed 60-day period. The subcontractor still has another 30 days beyond this date.

Option B: July 30th

July 30th represents 90 days after April 30th. While 90 days is the correct period for some other states, Louisiana's Private Works Act allows only 60 days from GC completion, making July 30th too late.

Option C: May 14th

May 14th represents 60 days after March 15th (the subcontractor's own completion date). This is the critical distractor—it uses the wrong start date. Louisiana law uses GC completion as the trigger, not the subcontractor's completion date.

Memory Technique

In Louisiana, a subcontractor's lien clock doesn't start when they leave the job—it starts when the GC leaves. Think of it as waiting for the 'captain of the ship' (GC) to depart before the 60-day countdown begins.

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.