A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?
Correct Answer
D) 20% plus attorney fees and court costs
Under Louisiana's Private Works Act, if a contractor prevails in a lien action, they may be awarded a penalty of 20% of the amount due plus attorney fees and court costs.
Why This Is the Correct Answer
Under Louisiana's Private Works Act, when a contractor successfully prevails in a lien action against a property owner, the court may award a penalty of 20% of the amount due plus attorney fees and court costs. This penalty provision is designed to encourage prompt payment and compensate contractors for the time and expense of pursuing legal action to collect unpaid amounts.
Why the Other Options Are Wrong
Option A: 15% plus court costs
The 15% penalty rate is incorrect under Louisiana law. While court costs may be recoverable, the statute specifically provides for a 20% penalty, not 15%. Additionally, this option doesn't include attorney fees, which are specifically allowed under the Private Works Act.
Option B: 25% plus all legal expenses
The 25% penalty rate exceeds what Louisiana law allows. The Private Works Act caps the penalty at 20% of the amount due. While legal expenses may be recoverable, the specific statutory language refers to attorney fees and court costs, not all legal expenses.
Option C: 10% plus attorney fees
The 10% penalty rate is too low and doesn't reflect Louisiana's statutory provision. The Private Works Act specifically allows for a 20% penalty, not 10%. While attorney fees are correctly included, court costs are also recoverable and should be mentioned.
Memory Technique
Remember 'Louisiana 20-20': 20% penalty plus attorney fees and court costs - like perfect vision for contractors collecting what they're owed.
More la-supplement Questions
A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?
A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?
Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?
A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?
Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?
Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?
A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?
A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?
A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?
A contractor discovers contaminated soil during excavation in Louisiana. Which state agency must be notified immediately?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In Louisiana, which of the following best describes the relationship between a general contractor and subcontractor regarding workers' compensation liability?
Next Question
Calculate the maximum lien amount a subcontractor can claim under Louisiana's Private Works Act for work valued at $80,000 when the total project cost is $300,000 and the contract between owner and general contractor is $275,000: