EstatePass
LouisianaLA Supplementhard100% of exam part

A material supplier delivered $15,000 worth of lumber on January 10th to a private construction project. The project was completed on March 1st. Under Louisiana's Private Works Act, what is the latest date the supplier can file their statement of claim?

Correct Answer

C) April 30th

Material suppliers have 60 days from project completion to file their statement of claim. Since the project completed March 1st, the deadline is April 30th.

Answer Options
A
May 1st
B
March 12th
C
April 30th
D
March 10th

Why This Is the Correct Answer

Under the Louisiana Private Works Act, materialmen and subcontractors have 60 days from the date of project completion (filing of the notice of termination or actual completion) to file their statement of claim and privilege. March 1 + 60 days = April 30. The date of lumber delivery is irrelevant to this deadline—the clock runs from project completion, not from the claimant's last work or delivery.

Why the Other Options Are Wrong

Option A: May 1st

May 1st would be 61 days from March 1st—one day past the 60-day deadline. Filing on May 1st would be untimely and the lien would be invalid. The exact deadline of April 30th must be respected.

Option B: March 12th

March 12th would be only 11 days after project completion, which is far too early for a deadline. This answer seems to confuse the filing deadline with some short notice period that does not exist under the Louisiana Private Works Act.

Option D: March 10th

March 10th is only 9 days after project completion and appears to be calculated from the delivery date (January 10th + 60 days = March 10th). This is a common trap—the 60-day period runs from project completion, not from the supplier's last delivery.

Memory Technique

Louisiana PWA clock starts at the project's END, not your delivery. Think: 'The whole project must be done before your 60-day countdown begins.' March 1 + 60 days—count on your fingers: March has 31 days, so 31 - 1 = 30 days left in March, then 30 more days in April = April 30.

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.