A contractor discovers lead-based paint during renovation of a 1965 Oregon home. The work area is 850 square feet. What EPA RRP certification is required?
Correct Answer
D) Basic RRP certification
EPA RRP certification is required for renovation work in pre-1978 housing that disturbs more than 6 sq ft of painted surfaces per room.
Why This Is the Correct Answer
Option D is correct. The EPA's Renovation, Repair, and Painting (RRP) Rule requires contractors working in pre-1978 homes to hold Basic RRP certification when disturbing more than 6 sq ft of painted surfaces per room (or 20 sq ft exterior). This home was built in 1965 (pre-1978), and 850 sq ft of work area far exceeds the 6 sq ft trigger.
Why the Other Options Are Wrong
Option A: Hazmat certification
Hazmat certification is not an EPA RRP category. It is a common distractor that sounds plausible for lead work but is not the correct regulatory classification under the RRP Rule.
Option B: Advanced RRP certification
There is no 'Advanced RRP certification' classification under EPA's RRP program. The program has Basic RRP certification (and a separate Lead Abatement certification for full removal, which is different).
Option C: No certification required
No certification required is incorrect. Pre-1978 housing with disturbed painted surfaces above the threshold triggers mandatory RRP compliance. Ignoring this exposes a contractor to EPA fines.
Memory Technique
Remember '78 is the line' β any home built before 1978 is in the RRP danger zone. Then remember '6 square feet per room' as the trigger (about the size of a small window frame). If you disturb more than that, you need Basic RRP.
More Oregon Questions
Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?
An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?
A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?
Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?
A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?
A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.
A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?
What is the minimum experience requirement for obtaining an Oregon CCB contractor license?
A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?
A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?