Before bidding a deck repair, the plan calls out one beam size but the existing posts are spaced differently. What is the best estimating response?

Correct Answer

A) Verify the condition and request clarification.

A conflict between plans and actual conditions should be clarified before pricing or building; field verification and an RFI are appropriate.

Answer Options
A
Verify the condition and request clarification.
B
Bid the smaller beam without notation.
C
Rough-opening verification.
D
Use a supplier quote as the design answer.

Why This Is the Correct Answer

A conflict between plans and actual conditions should be clarified before pricing or building; field verification and an RFI are appropriate.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.