A bid alternate changes the floor finish from vinyl plank to ceramic tile. What should the estimator compare?

Correct Answer

D) Changed cost and schedule impacts.

A real alternate affects more than material price; labor, accessories, substrate prep, and schedule impacts must be compared.

Answer Options
A
Unit-price backup.
B
Supplier lead time.
C
Contingency line.
D
Changed cost and schedule impacts.

Why This Is the Correct Answer

A real alternate affects more than material price; labor, accessories, substrate prep, and schedule impacts must be compared.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.