A custom sliding door package will be ordered before demolition starts. What should be verified first?

Correct Answer

B) Approved size and performance.

Long-lead materials should be ordered from approved dimensions and specifications to avoid expensive mismatch.

Answer Options
A
Only the delivery driver's route.
B
Approved size and performance.
C
Rough-opening verification.
D
Only the final cleaning schedule.

Why This Is the Correct Answer

Long-lead materials should be ordered from approved dimensions and specifications to avoid expensive mismatch.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.