A correction notice for missing hold-down hardware is still open, but insulation installation is scheduled. What should occur first?

Correct Answer

C) Get signoff.

Open structural corrections should be resolved before the work is concealed.

Answer Options
A
Approved fireblocking.
B
Boundary nailing.
C
Get signoff.
D
Collapse risk during erection.

Why This Is the Correct Answer

Open structural corrections should be resolved before the work is concealed.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.