Roof-to-wall clips shown on the approved plan are missing along one exterior wall. What is incomplete?

Correct Answer

C) Uplift tie.

Roof-to-wall connectors transfer uplift forces from the roof into the wall and foundation load path.

Answer Options
A
Continue framing where roof-to-wall clips shown on the approved plan are missing along one exterior wall, and wait for drywall to hide the framing defect.
B
Photograph the condition where roof-to-wall clips shown on the approved plan are missing along one exterior wall, but close the framing item without correcting the fastening or bearing condition.
C
Uplift tie.
D
Treat the item as layout cleanup where roof-to-wall clips shown on the approved plan are missing along one exterior wall, and let a later crew work around the framing condition.

Why This Is the Correct Answer

Roof-to-wall connectors transfer uplift forces from the roof into the wall and foundation load path.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.