A stud bay runs from a dropped ceiling into an attic space without draft stopping at the concealed passage. What is missing?

Correct Answer

C) Fireblocking.

Concealed vertical and horizontal passages may need fireblocking or draft stopping to slow hidden fire spread.

Answer Options
A
Load path.
B
Match approved detail.
C
Fireblocking.
D
Member capacity.

Why This Is the Correct Answer

Concealed vertical and horizontal passages may need fireblocking or draft stopping to slow hidden fire spread.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.