In the bathroom addition file, a backsplash has 28 device boxes, and each extension takes 8 minutes. How many labor hours are needed?

Correct Answer

B) 3.73 hours.

The work time is 28 x 8 = 224 minutes. Since 60 minutes equal 1 hour, 224 / 60 = 3.73 hours.

Answer Options
A
3.2 hours total.
B
3.73 hours.
C
4.2 hours total.
D
4.8 hours total.

Why This Is the Correct Answer

The work time is 28 x 8 = 224 minutes. Since 60 minutes equal 1 hour, 224 / 60 = 3.73 hours.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.