A slab vapor retarder is omitted where the plan calls for one under moisture-sensitive flooring. What should happen?

Correct Answer

D) Resolve before pour.

Specified below-slab moisture protection should be corrected before concrete placement conceals it.

Answer Options
A
Curing protection.
B
Hold for inspection.
C
Inadequate soil preparation.
D
Resolve before pour.

Why This Is the Correct Answer

Specified below-slab moisture protection should be corrected before concrete placement conceals it.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.