A rough inspection is scheduled, but insulation has already concealed plumbing and electrical work in several walls. What should be maintained?

Correct Answer

C) Open inspection.

Work that requires rough inspection should remain visible and accessible until the inspection is accepted.

Answer Options
A
Rated protection.
B
Required clearance.
C
Open inspection.
D
Restore airflow.

Why This Is the Correct Answer

Work that requires rough inspection should remain visible and accessible until the inspection is accepted.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.