A backfill area is placed in 24-inch loose lifts even though the compaction plan calls for thin controlled lifts. What is the risk?

Correct Answer

C) Poor compaction.

Backfill placed in overly thick lifts may not compact uniformly, causing settlement or performance issues.

Answer Options
A
Connector slack.
B
Damper function.
C
Poor compaction.
D
Discharge cooking exhaust outside.

Why This Is the Correct Answer

Backfill placed in overly thick lifts may not compact uniformly, causing settlement or performance issues.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.