A crew places concrete over standing water and mud in a footing trench. What should happen first?

Correct Answer

A) Prepare a clean bearing surface.

Footing concrete should be placed on a suitable prepared bearing surface, not over mud or standing water.

Answer Options
A
Prepare a clean bearing surface.
B
Add more water to the mix.
C
Leave the rough condition in place where a crew places concrete over standing water and mud in a footing trench, and leave the defect for closeout review.
D
Close the inspection item where a crew places concrete over standing water and mud in a footing trench, without checking the required installation before cover.

Why This Is the Correct Answer

Footing concrete should be placed on a suitable prepared bearing surface, not over mud or standing water.

Was this explanation helpful?

More ca-trade-b Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.