Concrete is placed on a hot, windy day and the surface begins drying before finishing. What should the superintendent focus on?
Correct Answer
D) Protect and cure the concrete.
Rapid surface drying can cause quality problems; concrete needs appropriate curing and protection after placement.
Why This Is the Correct Answer
Rapid surface drying can cause quality problems; concrete needs appropriate curing and protection after placement.
More ca-trade-b Questions
A 2-inch horizontal sanitary branch must be installed at 1/4 inch fall per foot. What total fall is needed over a 24-foot run?
A 4-inch building drain is laid out with a required 1/8 inch fall per foot. What fall is required across 40 feet?
A rooftop unit schedule shows 3 tons of cooling. Using 12,000 Btu per hour per ton, what cooling capacity is this?
A pump motor is listed as 2 horsepower, and the coordination table asks for watts. Using 746 watts per horsepower, what is the approximate motor power?
A slab is 30 feet long, 18 feet wide, and 4 inches thick. How many cubic yards of concrete are needed before waste?
A footing is 80 feet long, 2 feet wide, and 12 inches deep. How many cubic yards of concrete are required before waste?
A patio subgrade must drain at 2 percent away from the building for 20 feet. What total drop is required?
A building pad needs 150 compacted cubic yards of fill. If the borrow material shrinks 10 percent after compaction, about how many loose cubic yards should be hauled in?
A roofing estimate shows 2,850 square feet of roof area. How many roofing squares is that?
A waterproof deck surface is 14 feet deep and must slope 1/4 inch per foot to the drain. What vertical fall is needed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The housekeeping pad worksheet shows that the ready-mix order starts from a 13.33-cubic-yard concrete takeoff and adds 10 percent waste. What total order quantity results?
Next Question
A rated corridor wall is patched after plumbing work, and the patch uses ordinary board without matching the tested assembly. What must be maintained?