Originationmedium27% of exam

A borrower obtaining a Fannie Mae first mortgage at 72% loan-to-value requests a waiver of tax and property-insurance escrows. Assume no legal or program requirement prohibits this waiver. What should the borrower understand about approval and any waiver fee?

Correct Answer

C) Approval depends on lender policy and ability to pay property bills; any imposed waiver fee must be disclosed

C. A low LTV alone neither guarantees a waiver nor establishes that it is free. Fannie Mae requires a written waiver policy that considers financial ability to pay property charges, not solely LTV. For a covered Closing Disclosure, any fee imposed for waiving escrow is disclosed as an Escrow Waiver Fee. Scope and exceptions: The borrower remains responsible for timely property bills without escrow. Applicable law and specific program restrictions still control; the question excludes those prohibitions. A disclosure requirement does not require a lender to charge a fee or independently authorize a fee prohibited elsewhere. Source: Waiver of Escrow Requirements — https://guide-selling.fanniemae.com/sel/b2-1.5-04/escrow-accounts Section 1026.38(l)(7)(i)(B) — https://www.consumerfinance.gov/rules-policy/regulations/1026/38/

Answer Options
A
Always available on request, and never priced into the loan terms
B
Never available, because escrows are required on every mortgage loan
C
Approval depends on lender policy and ability to pay property bills; any imposed waiver fee must be disclosed
D
Available only above 80% loan-to-value, where the risk is greater

Why This Is the Correct Answer

C. A low LTV alone neither guarantees a waiver nor establishes that it is free. Fannie Mae requires a written waiver policy that considers financial ability to pay property charges, not solely LTV. For a covered Closing Disclosure, any fee imposed for waiving escrow is disclosed as an Escrow Waiver Fee. Scope and exceptions: The borrower remains responsible for timely property bills without escrow. Applicable law and specific program restrictions still control; the question excludes those prohibitions. A disclosure requirement does not require a lender to charge a fee or independently authorize a fee prohibited elsewhere.

Why the Other Options Are Wrong

Option A: Always available on request, and never priced into the loan terms

Neither automatic approval nor universal free pricing follows from the facts.

Option B: Never available, because escrows are required on every mortgage loan

Waivers are permitted in eligible circumstances.

Option D: Available only above 80% loan-to-value, where the risk is greater

The cited policy does not make an LTV above 80% a prerequisite.

Exam Tip

Verify waiver eligibility, payment ability and actual disclosed terms instead of assuming an LTV shortcut.

Was this explanation helpful?

More Origination Questions

Before the team acts on a servicing handoff check, a closing coordinator must address Asset Verification and Reserves. Which response is most defensible?

An MLO is reviewing procedures for a case where a cost changes after the Closing Disclosure has already been provided. What is the proper handling?

During a post-application update, a quality-control reviewer encounters a Credit Analysis and Evaluation issue. Which response should avoid a shortcut that would misapply the rule?

A construction-to-permanent loan will disburse in 5 draws over 11 months before the permanent phase begins. Which Regulation Z appendix provides a disclosure method for multiple-advance construction transactions?

Before closing, the team discovers that a borrower asks which upfront charge can be collected before intent to proceed. What is the safest compliant answer?

A construction loan agreement allows advances only after documented completion of specified work. A builder requests the next draw, but no completion evidence has been provided. What should occur?

Before releasing the final construction draw, which combination most directly supports project completion and clear collateral?

A construction-to-permanent loan will convert to a substantially higher fully amortizing payment. Which payment is especially important when assessing the borrower's long-term repayment capacity?

A construction-to-permanent note states that conversion requires completion, a certificate of occupancy, and no unresolved liens. Construction is finished, but a mechanic's lien remains. What should happen?

A branch manager asks about a loan file because a processor wants to omit known monthly obligations from underwriting. What should happen?

People Also Study

Related Study Resources

Practice More MLO Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your SAFE MLO exam.

Start Practicing