For a RESPA-covered escrow account, the ordinary annual computation year ends March 31. No default, foreclosure or bankruptcy exemption applies, and this is not a short-year statement. The servicer first submits the annual statement to the borrower on May 8. Was it timely?

Correct Answer

A) Late: the statement was due within 30 days of the computation year

A. It is late; the ordinary deadline was April 30. Count 30 days after March 31 to reach April 30. The first submission on May 8 is eight days after that deadline. Scope and exceptions: Section 1024.17(i)(2) contains exemptions and (i)(4) addresses short-year statements. The revised facts exclude these different situations. Source: 1024.17(i) introductory paragraph; (i)(2), (i)(4) — https://www.consumerfinance.gov/rules-policy/regulations/1024/17/

Answer Options
A
Late: the statement was due within 30 days of the computation year
B
On time: the statement is due within 60 days of the computation year
C
On time: annual statements are due by 30 June whatever the year end
D
Late: the statement was due within 15 days of the computation year

Why This Is the Correct Answer

A. It is late; the ordinary deadline was April 30. Count 30 days after March 31 to reach April 30. The first submission on May 8 is eight days after that deadline. Scope and exceptions: Section 1024.17(i)(2) contains exemptions and (i)(4) addresses short-year statements. The revised facts exclude these different situations.

Why the Other Options Are Wrong

Option B: On time: the statement is due within 60 days of the computation year

It substitutes 60 days for the ordinary 30-day rule.

Option C: On time: annual statements are due by 30 June whatever the year end

The rule is tied to this account’s computation year, not a universal June date.

Option D: Late: the statement was due within 15 days of the computation year

It uses a 15-day period that is not the stated rule.

Exam Tip

Identify the statement type before counting its deadline.

Was this explanation helpful?

More Origination Questions

Before the team acts on a servicing handoff check, a closing coordinator must address Asset Verification and Reserves. Which response is most defensible?

An MLO is reviewing procedures for a case where a cost changes after the Closing Disclosure has already been provided. What is the proper handling?

During a post-application update, a quality-control reviewer encounters a Credit Analysis and Evaluation issue. Which response should avoid a shortcut that would misapply the rule?

A construction-to-permanent loan will disburse in 5 draws over 11 months before the permanent phase begins. Which Regulation Z appendix provides a disclosure method for multiple-advance construction transactions?

Before closing, the team discovers that a borrower asks which upfront charge can be collected before intent to proceed. What is the safest compliant answer?

A construction loan agreement allows advances only after documented completion of specified work. A builder requests the next draw, but no completion evidence has been provided. What should occur?

Before releasing the final construction draw, which combination most directly supports project completion and clear collateral?

A construction-to-permanent loan will convert to a substantially higher fully amortizing payment. Which payment is especially important when assessing the borrower's long-term repayment capacity?

A construction-to-permanent note states that conversion requires completion, a certificate of occupancy, and no unresolved liens. Construction is finished, but a mechanic's lien remains. What should happen?

A branch manager asks about a loan file because a processor wants to omit known monthly obligations from underwriting. What should happen?

People Also Study

Related Study Resources

Practice More MLO Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your SAFE MLO exam.

Start Practicing