Originationmedium27% of exam

An escrow analysis shows a $310 shortage when the monthly escrow payment is $600. The borrower is current. If the servicer chooses the equal-monthly-installment repayment option under Regulation X, what is its minimum repayment period?

Correct Answer

A) At least 12 months

A. The equal-monthly-installment option requires at least 12 months. The $310 shortage is less than the $600 monthly escrow payment. The question selects installments rather than the separate 30-day repayment alternative. Scope and exceptions: The servicer may also leave this shortage outstanding. These alternatives do not give the borrower an unconditional right to choose. A shortage below a target balance is not the same as a negative-balance deficiency, which has different repayment rules. Source: Section 1024.17(b), (f)(3)(i) and (f)(4) — https://www.consumerfinance.gov/rules-policy/regulations/1024/17/

Answer Options
A
At least 12 months
B
The entire remaining loan term
C
Exactly 30 days
D
At least 24 months

Why This Is the Correct Answer

A. The equal-monthly-installment option requires at least 12 months. The $310 shortage is less than the $600 monthly escrow payment. The question selects installments rather than the separate 30-day repayment alternative. Scope and exceptions: The servicer may also leave this shortage outstanding. These alternatives do not give the borrower an unconditional right to choose. A shortage below a target balance is not the same as a negative-balance deficiency, which has different repayment rules.

Why the Other Options Are Wrong

Option B: The entire remaining loan term

The remaining mortgage term is not the required repayment period.

Option C: Exactly 30 days

Thirty-day repayment is a different permitted alternative.

Option D: At least 24 months

Twenty-four months can satisfy the rule, but is not its minimum.

Exam Tip

Identify shortage versus deficiency, then the size and chosen repayment option.

Was this explanation helpful?

More Origination Questions

Before the team acts on a servicing handoff check, a closing coordinator must address Asset Verification and Reserves. Which response is most defensible?

An MLO is reviewing procedures for a case where a cost changes after the Closing Disclosure has already been provided. What is the proper handling?

During a post-application update, a quality-control reviewer encounters a Credit Analysis and Evaluation issue. Which response should avoid a shortcut that would misapply the rule?

A construction-to-permanent loan will disburse in 5 draws over 11 months before the permanent phase begins. Which Regulation Z appendix provides a disclosure method for multiple-advance construction transactions?

Before closing, the team discovers that a borrower asks which upfront charge can be collected before intent to proceed. What is the safest compliant answer?

A construction loan agreement allows advances only after documented completion of specified work. A builder requests the next draw, but no completion evidence has been provided. What should occur?

Before releasing the final construction draw, which combination most directly supports project completion and clear collateral?

A construction-to-permanent loan will convert to a substantially higher fully amortizing payment. Which payment is especially important when assessing the borrower's long-term repayment capacity?

A construction-to-permanent note states that conversion requires completion, a certificate of occupancy, and no unresolved liens. Construction is finished, but a mechanic's lien remains. What should happen?

A branch manager asks about a loan file because a processor wants to omit known monthly obligations from underwriting. What should happen?

People Also Study

Related Study Resources

Practice More MLO Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your SAFE MLO exam.

Start Practicing