Originationmedium27% of exam

Before consummation of a regular transaction subject to TRID, a change to an APR-included charge raises the actual APR from the 6.412% disclosed on the Closing Disclosure to 6.545%. No separate APR-accuracy exception or valid waiting-period waiver applies. What must the creditor do?

Correct Answer

A) Provide a corrected Closing Disclosure received at least three business days before consummation

A. Correct the disclosure and satisfy a new three-business-day waiting period. The difference is 0.133 percentage point, exceeding the ordinary 0.125-point regular-transaction tolerance. An inaccurate APR is a specified trigger for a new waiting period; mere preparation or dispatch of the correction is not receipt. Scope and exceptions: Assess all APR-accuracy provisions before finding a real loan inaccurate. The assumed regular classification, not a fixed-rate label alone, determines the ordinary tolerance. Other changes may require correction without a new waiting period. Source: Section 1026.22(a)(2)–(5) — https://www.consumerfinance.gov/rules-policy/regulations/1026/22/ Section 1026.19(f)(2)(ii)(A) and comment 19(f)(2)(ii)-1 — https://www.consumerfinance.gov/rules-policy/regulations/1026/19/

Answer Options
A
Provide a corrected Closing Disclosure received at least three business days before consummation
B
Redisclose with no new waiting period, as only the loan product restarts it
C
No redisclosure: an APR difference under 0.25 is accurate on any loan
D
Redisclose and restart 7 days, which is the period for an APR change

Why This Is the Correct Answer

A. Correct the disclosure and satisfy a new three-business-day waiting period. The difference is 0.133 percentage point, exceeding the ordinary 0.125-point regular-transaction tolerance. An inaccurate APR is a specified trigger for a new waiting period; mere preparation or dispatch of the correction is not receipt. Scope and exceptions: Assess all APR-accuracy provisions before finding a real loan inaccurate. The assumed regular classification, not a fixed-rate label alone, determines the ordinary tolerance. Other changes may require correction without a new waiting period.

Why the Other Options Are Wrong

Option B: Redisclose with no new waiting period, as only the loan product restarts it

An inaccurate APR also triggers the wait.

Option C: No redisclosure: an APR difference under 0.25 is accurate on any loan

The 0.25-point rule is not universal.

Option D: Redisclose and restart 7 days, which is the period for an APR change

Seven days is not this correction's waiting period.

Exam Tip

First test APR accuracy; then determine the required correction timing.

Was this explanation helpful?

More Origination Questions

Before the team acts on a servicing handoff check, a closing coordinator must address Asset Verification and Reserves. Which response is most defensible?

An MLO is reviewing procedures for a case where a cost changes after the Closing Disclosure has already been provided. What is the proper handling?

During a post-application update, a quality-control reviewer encounters a Credit Analysis and Evaluation issue. Which response should avoid a shortcut that would misapply the rule?

A construction-to-permanent loan will disburse in 5 draws over 11 months before the permanent phase begins. Which Regulation Z appendix provides a disclosure method for multiple-advance construction transactions?

Before closing, the team discovers that a borrower asks which upfront charge can be collected before intent to proceed. What is the safest compliant answer?

A construction loan agreement allows advances only after documented completion of specified work. A builder requests the next draw, but no completion evidence has been provided. What should occur?

Before releasing the final construction draw, which combination most directly supports project completion and clear collateral?

A construction-to-permanent loan will convert to a substantially higher fully amortizing payment. Which payment is especially important when assessing the borrower's long-term repayment capacity?

A construction-to-permanent note states that conversion requires completion, a certificate of occupancy, and no unresolved liens. Construction is finished, but a mechanic's lien remains. What should happen?

A branch manager asks about a loan file because a processor wants to omit known monthly obligations from underwriting. What should happen?

People Also Study

Related Study Resources

Practice More MLO Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your SAFE MLO exam.

Start Practicing