A creditor receives a TRID application on Monday, April 6. Its offices are open to the public for substantially all business functions Monday through Friday only. No holiday falls in this period. For the initial Loan Estimate, which deadline and business-day definition apply to delivery or mailing within three business days after receipt?

Correct Answer

B) Thursday, April 9: use days open for substantially all business functions

B. Thursday, April 9, using the general business-day definition. Exclude receipt day: Tuesday is day one, Wednesday day two and Thursday day three. The calculation tests both the date and the correct definition. Scope and exceptions: This is the initial delivery-or-mailing deadline, not proof of receipt. Other TRID periods use a different definition. Limited services at an open office do not necessarily satisfy the business-function test. Source: Section 1026.2(a)(6); comment 2(a)(6)-1 — https://www.consumerfinance.gov/rules-policy/regulations/1026/2/ Section 1026.19(e)(1)(iii)(A) — https://www.consumerfinance.gov/rules-policy/regulations/1026/19/

Answer Options
A
Friday 10 April, since the day of receipt is excluded from the count
B
Thursday, April 9: use days open for substantially all business functions
C
Wednesday 8 April, counting every calendar day except Sunday
D
Thursday 9 April, because Saturday counts and Sunday does not

Why This Is the Correct Answer

B. Thursday, April 9, using the general business-day definition. Exclude receipt day: Tuesday is day one, Wednesday day two and Thursday day three. The calculation tests both the date and the correct definition. Scope and exceptions: This is the initial delivery-or-mailing deadline, not proof of receipt. Other TRID periods use a different definition. Limited services at an open office do not necessarily satisfy the business-function test.

Why the Other Options Are Wrong

Option A: Friday 10 April, since the day of receipt is excluded from the count

Excluding Monday does not add a fourth day.

Option C: Wednesday 8 April, counting every calendar day except Sunday

Wednesday is only the second day after receipt.

Option D: Thursday 9 April, because Saturday counts and Sunday does not

The date coincides, but its stated definition is wrong for this deadline.

Exam Tip

Identify the deadline before choosing a business-day definition.

Was this explanation helpful?

More Origination Questions

Before the team acts on a servicing handoff check, a closing coordinator must address Asset Verification and Reserves. Which response is most defensible?

An MLO is reviewing procedures for a case where a cost changes after the Closing Disclosure has already been provided. What is the proper handling?

During a post-application update, a quality-control reviewer encounters a Credit Analysis and Evaluation issue. Which response should avoid a shortcut that would misapply the rule?

A construction-to-permanent loan will disburse in 5 draws over 11 months before the permanent phase begins. Which Regulation Z appendix provides a disclosure method for multiple-advance construction transactions?

Before closing, the team discovers that a borrower asks which upfront charge can be collected before intent to proceed. What is the safest compliant answer?

A construction loan agreement allows advances only after documented completion of specified work. A builder requests the next draw, but no completion evidence has been provided. What should occur?

Before releasing the final construction draw, which combination most directly supports project completion and clear collateral?

A construction-to-permanent loan will convert to a substantially higher fully amortizing payment. Which payment is especially important when assessing the borrower's long-term repayment capacity?

A construction-to-permanent note states that conversion requires completion, a certificate of occupancy, and no unresolved liens. Construction is finished, but a mechanic's lien remains. What should happen?

A branch manager asks about a loan file because a processor wants to omit known monthly obligations from underwriting. What should happen?

People Also Study

Related Study Resources

Practice More MLO Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your SAFE MLO exam.

Start Practicing