A covered non-timeshare mortgage will consummate Thursday, March 12. No legal public holiday or valid emergency waiver applies. What is the latest day the consumer may receive the initial Closing Disclosure and still satisfy the ordinary three-business-day waiting requirement?

Correct Answer

B) Monday 9 March, three business days before consummation

B. Receipt by Monday, March 9 satisfies the ordinary deadline. After Monday receipt, Tuesday, Wednesday and Thursday are the three counted business days. The rule concerns receipt, not merely dispatch on Monday. Scope and exceptions: For this requirement, Saturdays count and Sundays and specified legal public holidays do not; office opening hours are irrelevant. Non-personal delivery has a receipt presumption unless earlier receipt is evidenced. Count delivery and waiting separately. Source: Section 1026.19(f)(1)(ii)–(iii); comments 19(f)(1)(ii)-1 and -2 — https://www.consumerfinance.gov/rules-policy/regulations/1026/19/

Answer Options
A
Tuesday 10 March, two business days before consummation
B
Monday 9 March, three business days before consummation
C
Wednesday 11 March, the day before consummation
D
Thursday 5 March, seven business days before consummation

Why This Is the Correct Answer

B. Receipt by Monday, March 9 satisfies the ordinary deadline. After Monday receipt, Tuesday, Wednesday and Thursday are the three counted business days. The rule concerns receipt, not merely dispatch on Monday. Scope and exceptions: For this requirement, Saturdays count and Sundays and specified legal public holidays do not; office opening hours are irrelevant. Non-personal delivery has a receipt presumption unless earlier receipt is evidenced. Count delivery and waiting separately.

Why the Other Options Are Wrong

Option A: Tuesday 10 March, two business days before consummation

Tuesday receipt leaves only two counted days through Thursday.

Option C: Wednesday 11 March, the day before consummation

Wednesday receipt leaves only one counted day.

Option D: Thursday 5 March, seven business days before consummation

Thursday, March 5 is earlier than the latest required receipt date; seven days is not this CD interval.

Exam Tip

Distinguish the date sent from the date received before counting the waiting period.

Was this explanation helpful?

More Federal Laws Questions

People Also Study

Related Study Resources

Practice More MLO Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your SAFE MLO exam.

Start Practicing