The panel is where the inspector earns the fee: cover off (when safe), and the findings parade — double-taps, neutrals and grounds mingling where they must not, breakers oversized for their wires, and the rule that separates service equipment from subpanels.
What this video covers
- The neutral-ground rule
- Breakers and conductors
- Panel conditions and safe practice
Key takeaways
- Main: neutral-ground bonded; sub: isolated neutrals, 4-wire feed
- 14/15, 12/20, 10/30 conductor-breaker pairs
- Double-taps and double-lugged neutrals reported
- Heat discoloration = failing connections
- Open knockouts, wrong screws, water entry, access blockage
- Dead-front removal only when safe; limitation otherwise