You discover that a subcontractor has installed plumbing that doesn't meet Michigan code requirements. As the general contractor, what is your primary responsibility?
Correct Answer
C) Require the subcontractor to correct the work to meet code
As the general contractor, you are responsible for ensuring all work meets code requirements and must require the subcontractor to correct any non-compliant work before proceeding.
Why This Is the Correct Answer
As the general contractor (GC), you are the party of record responsible for delivering a code-compliant project to the owner. Michigan residential builder law holds the GC accountable for all work on the project, including work performed by subcontractors. When non-compliant work is discovered, the primary obligation is to direct the responsible subcontractor to correct it immediately — before proceeding with other work that might conceal or depend on the deficient installation.
Why the Other Options Are Wrong
Option A: Accept the work since it was done by a licensed subcontractor
Accepting the work simply because a licensed subcontractor performed it is incorrect. Licensure of the subcontractor does not transfer the GC's liability or oversight responsibility. The GC remains accountable to the owner and the building official for code compliance on all work performed under the contract.
Option B: Complete the project and address issues during the final inspection
Completing the project and addressing issues during final inspection is unacceptable. Continuing work over known non-compliant installations can make corrections more costly, may cause additional code violations, and exposes the GC to liability for concealing defects. Inspectors expect compliance to be corrected when discovered, not deferred.
Option D: Report the subcontractor to the state licensing board immediately
Immediately reporting the subcontractor to the state licensing board is not the primary responsibility at the time of discovery. The first priority is correcting the non-compliant work. Regulatory reporting may be warranted later if the subcontractor refuses to correct the work or if the violation is egregious, but it is not the primary first step.
Memory Technique
GC Rule: 'Your project, your code compliance.' When a sub does bad work, your first move is always: FIX IT. Report later if needed, but fix first. Think of it as: GC = General Corrector of all problems on site.
More mi-builder Questions
A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?
A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?
What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?
According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?
A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?
According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?
A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?
A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?
During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?
A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
You are framing a residential structure with 2x10 floor joists spaced 16 inches on center. The span is 14 feet with a live load of 40 psf and dead load of 10 psf. What is the total load per linear foot on the supporting beam?
Next Question
During construction of a residential deck in Michigan, the building inspector notes that the ledger board attachment may not meet code. What is the primary structural concern with improper ledger board attachment?
