Which statement about mechanics liens under California Civil Code is correct?
Correct Answer
B) Preliminary notices are required for most projects
California Civil Code requires preliminary notices to be served to preserve lien rights on most construction projects.
Why This Is the Correct Answer
Preliminary notices (also called 20-day preliminary notices) are required for most private construction projects so that subcontractors, material suppliers, and laborers can preserve their right to file a mechanics lien. Without serving a timely preliminary notice, most claimants lose their lien rights entirely.
Why the Other Options Are Wrong
Option A: Liens must be filed before work is completed
Liens do NOT need to be filed before work is completed. California Civil Code gives claimants a window after completion (90 days for direct contractors, 90 days after cessation of labor or recordation of a notice of completion for subcontractors and suppliers) to record their lien.
Option C: Liens automatically expire after 6 months
Liens do not automatically expire after 6 months. A recorded mechanics lien expires after 90 days unless a lawsuit to enforce the lien is filed within that period; the timeframe is 90 days, not 6 months.
Option D: Liens can only be filed by general contractors
Mechanics liens are NOT limited to general contractors. Subcontractors, material suppliers, equipment lessors, and laborers can all file mechanics liens, provided they have served the required preliminary notice.
Memory Technique
Think '20 days to notice, 90 days to lien.' The preliminary notice is your early reservation of rights β file it within 20 days of starting work or lose your lien rights.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
