EstatePass
Contract AdminProceduresmedium13% of exam part

When should as-built drawings be updated during construction?

Correct Answer

C) Continuously as changes occur during construction

As-built drawings should be updated continuously as changes occur to ensure accuracy and completeness. Waiting until project completion may result in forgotten details or inaccurate documentation.

Answer Options
A
Only when requested by the owner
B
Monthly during progress meetings
C
Continuously as changes occur during construction
D
Only at project completion

Why This Is the Correct Answer

As-built drawings must be updated continuously throughout construction to maintain accuracy and completeness. Construction projects involve numerous field changes, modifications, and unforeseen conditions that deviate from original plans. If updates are delayed, critical details may be forgotten or incorrectly documented, leading to inaccurate record drawings. Continuous updating ensures that all changes are captured in real-time while the information is fresh and accurate.

Why the Other Options Are Wrong

Option A: Only when requested by the owner

Monthly updates during progress meetings are insufficient because construction changes occur daily, and waiting a month between updates means many critical details and modifications could be forgotten or incorrectly documented.

Option B: Monthly during progress meetings

Waiting until project completion to update as-built drawings is problematic because many construction details and changes will be forgotten by that time, leading to incomplete or inaccurate documentation that fails to reflect actual field conditions.

Option D: Only at project completion

Relying solely on owner requests for as-built updates is inadequate because the owner may not be aware of all field changes, and the contractor has a professional responsibility to maintain accurate construction documentation regardless of specific requests.

Memory Technique

Think 'ABC' - As-Built drawings need Continuous updates, not 'ABE' - As-Built at End

Reference Hint

Florida Building Code, Chapter 1, Section 107 - Submittal Documents, or AIA Document A201 - General Conditions, Article 3.11 - Record Documents

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.