A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
Correct Answer
D) 500 miles
Under LEED standards, materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within 500 miles of the project site.
Why This Is the Correct Answer
LEED (Leadership in Energy and Environmental Design) standards specifically define regional materials as those that are extracted, harvested, or recovered AND manufactured within 500 miles of the project site. This 500-mile radius requirement is established to encourage the use of local materials, which reduces transportation costs and environmental impact while supporting the local economy. Both extraction/harvesting AND manufacturing must occur within this 500-mile radius to qualify as regional materials under LEED certification requirements.
Why the Other Options Are Wrong
Option A: 300 miles
100 miles is too restrictive and would severely limit material options for most projects, making it impractical for LEED compliance.
Option B: 1000 miles
300 miles is less than the actual LEED requirement and would unnecessarily restrict the pool of qualifying regional materials.
Option C: 100 miles
1000 miles exceeds the LEED standard and would be too broad to effectively promote local sourcing and reduce transportation impacts.
Memory Technique
Think 'LEED 500' - the number 500 rhymes with 'LEED' and represents the maximum miles for regional materials (both sourcing and manufacturing)
Reference Hint
Look up LEED Green Building Rating System or sustainable construction practices chapter in your contractor reference manual
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
A project has a total duration of 120 days. If the critical path is compressed by 10 days through crashing activities at an additional cost of $25,000, and the daily overhead cost is $800, what is the net cost impact?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
